Phase 1 (Now "Stairway to Heaven" is only a song)
Joe DeLoach
The summer of 2000 marked the completion of the first phase of one of the more
unusual and involved projects undertaken along the Appalachian Trail. The
Konnarock Volunteer Trail Crew and the Tennessee Eastman Hiking Club (TEHC)
opened the first section of a Trail relocation and rehabilitation project in the
Roan Mountain area. Over the course of three weeks this summer, most of
the steps leading steeply from the parking area at Carvers Gap to the first
summit, Round Bald, were replaced with a more gradual sidehill
trail. The quarter-mile distance to a large rock providing a vantage point
was roughly doubled by this relocation.
Well, what's so unusual about a half-mile sidehill Trail relocation?
The three weeks of actual construction was a drop in the bucket, compared to
the years that TEHC, ATC, and the Forest Service worked for approval of this
relocation. The section that was to be replaced was constructed by a crew
from the Appalachian Mountain Club of New Hampshire in 1976. That crew
built steps most of the way up 5,826-foot Round Bald. The steps were
stable, but many hikers in this high-use, open area walked off the Trail onto
the grassy bald, forming ditches. The high use, the soft organic
soils, and the heavy precipitation in the area all contributed to serious
erosion problems. Even with filling in the eroded areas, the Trail
partners felt that hikers would continue to wander off the steep steps, and the
erosion problems would persist and worsen.
A Trail relocation was called for, but it would be far from routine.
Konnarock and TEHC had installed a
relocation on the back side of Round Bald in
1992, using standard sidehill construction techniques and grades. Within
two years, that relocation had become very slick in places and rocky in
others. Hikers started walking around that section also, leading to a
braided Trail and erosion. In 1995, TEHC hardened an 85-foot section of
that relocation, using geotextile to line the treadway with gravel on
top. The relocation has held up very well in the ensuing five
years. But, that 85-foot section required ten tons of gravel for
fill! That gravel was transported to the site using a vehicle resembling
a military half-track, with the thinking that it would dig into the soils less
than a truck. However, the three trips required to haul the gravel
churned up the soil badly, and the entire project was going to require 300 tons
of gravel! Driving up the existing A.T. was not an option, because
removing the steps would cause massive erosion to occur. Clearly, another
way to get the gravel up the bald was needed.
The answer came from the Forest Service in the form of motorized
wheelbarrows or "Georgia buggies". These vehicles have a narrow
wheelbase but are still capable of carrying several hundred pounds of gravel
per load. The relocation needed to be wide enough to accommodate the
heavy hiker traffic, and that width also had to be sufficient for the Georgia
buggies. They would be used to build the Trail up from the Carvers Gap
parking area where the gravel was staged. Driving subsequent loads over
the gravel packed it down, but the surface is still porous enough to allow
water to pass through.
Flagging the relocation was also a major challenge. Keeping the Trail
in open balds would have required numerous switchbacks, and there was very
little vegetation to deter hikers from shortcutting them. Because of the
numerous rare species on Round Bald, both in the meadows and adjacent woods
where the Trail needed to be routed, it took nearly five years of working with
Forest Service biologists, other conservation organizations, and interested
naturalists to select a route acceptable to all parties. (A rare
tarantula was discovered near the route.)
With a flagline approved and the logistics worked out, the work began in
July. For the most part, the actual
digging was done using a trackhoe,
which cut the path to the proper width while leaving the sod in good shape for
reseeding the old A.T., and saved a lot of Konnarock and TEHC effort. The
gravel was loaded onto the Georgia buggies, which crew members were trained to
operate safely, using a front-end loader provided by TEHC volunteer Frank
Oglesby. The geotextile was laid in place, and the gravel was dumped and
spread onto it, proceeding uphill. In a few places, turn-outs were built
to allow the Georgia buggies to pass without impacting the delicate soils on
the bald. Logs from the steps were used to stabilize the gravel on
steeper slopes. Many rocks were encountered in the woods, but, through a
special rock-cracking device and old-fashioned sledgehammering and prying, they
were removed and used for stabilizing the outslope. In wet areas, drains
were installed to carry water under the Trail, and, in two especially wet
areas, "geoweb" - a thick, synthetic, cellular fabric that enables
transport of water through the Trail while providing a stable surface -
was used under the normal geotextile and gravel. Fences and replanted
vegetation were used to keep hikers on the new Trail and deter the ditch
formation that plagued the old Trail. With three weeks of Konnarock-crew
assistance, we reached the existing Trail at a large rock about two-thirds of
the way up Round Bald. The old Trail below that point was resodded, and
the new Trail was opened.
TEHC has received numerous compliments about the relocation. We had
feared that hikers would not go into the woods, but that turned out to be one
of prettiest parts. Paul Bradley, district manager for the Appalachian
Ranger District of the Pisgah National Forest in North Carolina, said,
"Hallelujah!" His district and the Nolichucky/Unaka district of
the Cherokee National Forest in Tennessee worked for years to get the necessary
approvals and addressed a series of resource challenges along the way.
Morgan Sommerville, ATC Deep South regional representative, said "It was a
long time coming, but worth the wait."
There is still much to be done in this area. TEHC is working on a
relocation on the other side of the road at Carvers Gap, and a major relocation
is planned to descend Grassy Ridge, which also has become very eroded.
Finishing the Round Bald relocation/rehab to Engine Gap will be a
challenge. The work slowed down considerably as the distance from Carvers
Gap grew, and logistics may necessitate a helicopter for delivery of gravel in
the future.
During the three-week project, TEHC had 42 volunteers who worked more than
1,000 hours, records for us both in numbers of workers and in time providing
support for the Konnarock crew. We had help from Scout troops,
Appalachian State University, and the North Carolina Bridge Crew for youthful
offenders.
Ed Oliver of TEHC was our project manager. In addition to working ten
days on the ground, he spent countless hours working with our agency partners
to design the route and get the needed approvals. We had very good
Konnarock crews on this project led by Josh Adams, who did a great job with
coordinating all the various tasks and workers. Both Forest Service
ranger districts in Tennessee and North Carolina put a lot of effort into
getting the approvals while protecting the resource, which was what the
relocation was all about.
Finally, Morgan Sommerville gets much of the credit. He persevered
through the dark days when it looked like we would not be able to do the
relocation and raised much of the funds necessary for the unprecedented project
design. His keeping the faith helped us all replace the "Stairway to
Heaven" with a good Trail we can be proud of.
Joe DeLoach is the Konnarock-crew liaison for the Tennessee Eastman
Hiking Club and has worked at least five days with the crew every year since
1992.
TEHC
Cofounder Earns a T-shirt at 89
By Bill Stowell
Tennessee Eastman Hiking Club
Frank Oglesby, who helped start the
Tennessee Eastman Hiking Club Appalachian
Trail more than 50 years ago, celebrated his eighty-ninth birthday
during a lunch break while working with the Konnarock crew this year on
the Round Bald relocation project. During lunch, TEHC member Ed
Oliver surprised Oglesby with a birthday carrot cake that was shared
with members of the club and Konnarock crew working that day.
Oglesby was an integral part of this
year's work, providing his own front-end loader, which was used to load
the gravel buggies that carried 250 tons of gravel up Round Bald to
build the new trail. During the execution of the project, he
worked 10 days with the Konnarock crew, becoming the oldest person to
earn a crew T-shirt this season. In fact, according to ATC's
records, Oglesby is the most senior (or, as we in TEHC like to
think...most experienced) volunteer ever to earn a crew T-shirt, by five
to seven years! He is also one of the club members chosen for
ATC's 75th anniversary honor roll.
|
More photos of work on Phase 1 of this relocation (click on the small photo to see a
larger one):
"Phase 2"
Photos of work on Phase 2 of this relocation (click on the small photo to see a
larger one):
 |
We had our share of troubles; here is a photo of the
track on an
Alltrack, off the drive gear (135KB). Photo courtesy of Steve
Wilson. |
 |
Tensioning gear on an Alltrack (169KB).
Photo courtesy of
Steve Wilson. |
|
Bob Peoples navigating an Alltrack on the rocky and muddy terrain on Round Bald
(183KB). Photo courtesy of Steve Wilson. |
 |
Carl Fritz watches the front-end loader
transfer gravel to an Alltrack (150KB). Photo courtesy of Steve Wilson. |
 |
Carl Fritz at the controls of an
Alltrack in Carvers Gap (89KB). Photo courtesy of Steve Wilson. |
 |
Sign describing another relocation
trail-south of Carvers Gap (102KB). Photo courtesy of Steve Wilson. |
 |
Front-end loader and piles of gravel in
Carvers Gap (136KB). Photo courtesy of Steve Wilson. |
 |
A view trail-north towards the summit
of Round Bald, showing the tread marks left by the Alltracks.
There should be no trace of these within a year or two (181KB). Photo courtesy of Steve Wilson. |
 |
Carl Fritz (left) and Ed Oliver (right)
building the fence which blocks the old trail. Carvers Gap is in
the background (216KB). Photo courtesy of Steve Wilson. |
 |
An Alltrack descending Round Bald
towards Carvers Gap (126KB). Photo courtesy of Steve Wilson. |
 |
Bob Peoples driving an Alltrack towards
Carvers Gap (251KB). Photo courtesy of Steve Wilson. |
 |
Bob Peoples continuing descent towards
Carvers Gap (232KB). Photo courtesy of Steve Wilson. |
 |
David Gibson ascends Round Bald with a
load of gravel (202KB). Photo courtesy of Steve Wilson. |
 |
Sign in Carvers Gap, with front-end
loader and piles of gravel in background (131KB). Photo courtesy of Steve Wilson. |
 |
Another view of the sign in Carvers Gap
(118KB). Photo courtesy of Steve Wilson. |
 |
New location of A.T. in Carvers Gap
(210KB). Photo courtesy of Steve Wilson. |
 |
A.T. crossing of Tenn. 143 in Carvers
Gap from north side of road (98KB). Photo courtesy of Steve Wilson. |
 |
A.T. crossing of Tenn. 143 in Carvers
Gap from south side of road (95KB). Photo courtesy of Steve Wilson. |
 |
Visitor kiosk in Carvers Gap
(98KB). Photo courtesy of Steve Wilson. |
 |
Morgan Sommerville using a cell phone,
while atop a gravel pile in Carvers Gap (78KB). Photo courtesy of Steve Wilson. |
 |
(Left to right) Steve Perri, Morgan
Sommerville, David Gibson, Carl Fritz, and Ed Oliver (81KB). Photo
courtesy of Steve Wilson. |
 |
Descending from Carvers Gap north into
Tennessee on Tenn. 143 (71KB). Photo courtesy of Steve Wilson. |
 |
Descending from Round Bald
towards Carvers Gap, showing the snowcat-loads of gravel that were
deposited at 30 foot intervals, April 10, 2001 (87KB). Photo courtesy of
Verlin and Judy Howell. |
 |
Round Bald relocation, near
Carvers Gap, April 10, 2001 (84KB). Photo courtesy of Verlin
and Judy Howell. |
 |
Round Bald relocation, showing
the transition between bald and forest, April 10, 2001 (139KB). Photo courtesy of
Verlin and Judy Howell. |
 |
Another shot of the Round Bald
relocation, showing the transition between bald and forest, April
10, 2001 (74KB). Photo courtesy of Verlin and Judy Howell. |
